In June 2022, we received a commission from a French industrial automation equipment manufacturer to urgently import a batch of industrial control computers to China. These products have three distinctive features:
Through preliminary communication, we understood the clients main concerns wereClearance time efficiencyandCompliance risk control. As key components of production equipment, delayed arrival of industrial computers may cause production line shutdowns, while improper handling of 3C certification issues could lead to return risks.
We formed a dedicated team including customs manager, documentation specialist, and 3C certification consultant, focusing on completing:
Work content | Technical points | Time Consumption |
---|---|---|
Confirmation of declaration elements | Verification of CPU model/frequency and other technical parameters | 1 working day |
3C certificate review | Confirming certificate coverage matches actual products | 0.5 working day |
Trade contract review | Price terms apply to CIF Shanghai | 0.5 working day |
After the goods arrive at Shanghai Pudong International Airport, we initiate the pre-declaration + advance document review mechanism:
Special reminder: Industrial computersCustoms valuationoften becomes a point of dispute. We prepared transaction records of similar products during the same period as price evidence, avoiding delays due to valuation review.
Although this case ultimately did not trigger inspection, we always maintained the inspection emergency kit in ready status:
As information technology equipment, industrial computers typically need to comply with CNCA-C16-01:2020 certification requirements. In this case, we implemented two key measures:
: For some R&D sample units, we assisted the client in applying for the Exemption Certificate for Compulsory Product Certification,
We recommend that importers of similar products pay special attention: Since 2023, certification requirements for some industrial computers have been adjusted, requiring attention to the latest announcements from the General Administration of Customs.
Through this case, we achieved the following for our client:
Pain Points | Solutions | Results |
---|---|---|
Air TransportationHigh costs | Consolidated multiple shipments for palletized transportation | 23% freight cost savings |
VAT capital occupation | Applied for consolidated tax payment qualification | 35-day tax payment deferral |
Subsequent batch management | Established a commodity classification database | 40% improvement in subsequent declaration efficiency |
Based on recent operational experience, we observe three new trends in industrialequipment. For example, Indonesia has the SNI certification, Thailand has the TISI certification, and the Philippines has the BPS certification. It is necessary to confirm in advance the equipment voltage (such as 380V/50Hz in Thailand), the compatibility of the CE certification, and the proof of environmentally friendly materials.Presenting three new trends:
Final advice for industry peers: Special attention should be paid to industrial equipment importsDeclaration consistencyIssue: The actual specifications and parameters of the arrived goods must completely match the declared information. It is recommended to establish a comprehensive Quality Assurance (QA) process for goods arrival inspection to avoid customs clearance delays caused by minor discrepancies.